# Record costs and income

Log the money a project spends and the money it brings in, so the project's margin is always current.

Source: https://support.rework.com/article/record-costs-and-income

Effort is only half of what a project costs. The other half is everything you buy for it: licences, stock photography, a testing lab, a freelancer's invoice. **Costs** collects that spend beside the labour already booked as workloads, and **Incomes** records the money coming back in, anchored to the milestone that earns it. Keep both current and the project's margin is a fact rather than a guess. Here's how to record them.

> **Note:** Every amount is shown in the project's currency. Set it once in the project **Settings**, see [Set the project billing and units](https://support.rework.com/article/set-the-project-billing-and-units).

## Step 1: Open the Costs register

- Open the project and click **Costs** in the project menu.
  
- The **Filters** rail lists the categories actually in use, with a count each, and filters by **Board**, **Status** and **Owner**.
  
- Click **Add expense** to record a new one.
  

![The Costs register of Atlasworks Website Redesign with the filter rail and the Add expense button](https://storage.googleapis.com/reworkv3-public/success/260923/0rsNv0PIgdMEEVWfPdTN5sYSDJqHs2RU79U29THKuWp54SdGlJykIk2pO16oTZE2/img.Cam0A1zX774bPQveu26S5SIRjcNlugaOUXYBgOCcAaAhLYDVHQvDfOmdTif6f1Cz.png)

## Step 2: Describe the expense and its amount

In the **Add expense** dialog:

- **Name**: what the money is for, for example _Usability testing lab_.
  
- **Quantity** and **Rate**: how many units and the price per unit.
  
- **Amount**: quantity × rate. It updates as you type, and you can type the figure in directly when there's no sensible unit price.
  
- **Currency**: the ISO currency of the expense. When the project locks bookings to its own currency, this field is fixed.
  

![Name, Quantity, Rate, Amount and Currency in the Add expense dialog](https://storage.googleapis.com/reworkv3-public/success/260923/xdtwsSFdmz03TPCJzlJH5P006PLEiPNfijhCWiSVAyVKZmpGG1edJw4Xr5GeryQ8/img.7CkjcX3C5laLDBjl3vYUBWD10LTzLO05cmwJjOZWkoKcQoWggnteCZKerXFMOGzE.png)

## Step 3: Choose a category and a status

- **Category** sorts the spend in the rail and in reporting. Pick one of **Capex**, **Opex**, **Vendor**, **Labor**, **Infra** or **Other**. An expense with no category is grouped as **Uncategorized**.
  
- **Status** works exactly like a workload's: **Planned** for spend you expect, **Booked** for spend that's committed, and **Recorded** for money actually paid. A new expense starts as **Booked**.
  

![The Category list open with Capex, Opex, Vendor, Labor, Infra and Other, next to the Status field](https://storage.googleapis.com/reworkv3-public/success/260923/mPqp6mgUHiKwS12mpAlirGsI8EniHxT2JUa5NcIUKlX58AMZl4zVF6SNQ9PbkYaZ/img.ZLvAeWuzJst0WhtmyQAfcsE3jAAPH7ZwSxZB1OWOTBZnLsxagmrnY2DyCzrOBKbZ.png)

| Category | Typical use in a studio |
| --- | --- |
| **Capex** | Equipment bought for the project. |
| **Opex** | Running costs such as subscriptions. |
| **Vendor** | A supplier or freelancer invoice. |
| **Labor** | People costs entered as money rather than as a workload booking. |
| **Infra** | Hosting, environments, tooling. |
| **Other** | Anything that fits nowhere else. |

## Step 4: Set the owner and the period, then save

- **Owner**: who holds this cost, usually whoever approves or receives the invoice.
  
- **Period start** and **Period end**: the window the spend belongs to. Reports read this for phasing.
  
- **Description**: invoice references, supplier details, anything that explains the number later.
  

Click **Add expense**.

![Owner, Period start, Period end and the Add expense button](https://storage.googleapis.com/reworkv3-public/success/260923/Wv5AlZaiU1jJYOYnTsc8WdNgjdsdybVRhgH0MTO9jmmScXUX5dSmCObvMnHQMRbk/img.6EarRGck1ePpZaKyfvxPFxEVgxJ60hJJwYZFF9BaV7oJy0tcD2W3MFss7CCZzP24.png)

## Step 5: Read the register

The Costs register shows more than expenses. Every workload booked on the project appears here too, because labour is a cost:

- A row tagged **EXPENSE** is money you entered here.
  
- A row tagged **WORKLOAD** is a booking from [Book workloads](https://support.rework.com/article/book-workloads), shown in the **Labor** category with its effort, for example _Labor · 12 day_.
  
- **Booked** is the committed amount. **Recorded** is what has actually been paid or consumed, and stays blank until the record is marked **Recorded**.
  

That's why the Costs page is the single answer to "what is this project costing us?", while the Workloads page answers "who is doing the work?".

![The Costs register with the new EXPENSE row, a WORKLOAD row, and the Booked and Recorded figures of a recorded row](https://storage.googleapis.com/reworkv3-public/success/260923/fxMC5JckNC8v4cEgpjrfAFN26Z1m0edIPWUdT56uj7jhfJ2ldHUa0malZPk1ofES/img.Nsvmv3nvKyKqfQC6eW6jZdZ6R8hNjesW3BFTsk2hlfJbW1VEbsKljSEtaQVdybud.png)

## Step 6: Open the Incomes register

Click **Incomes** in the project menu. Each line shows its **Code**, the income, the **Milestone** it's recognised at, its **Status**, the **Owner** and the **Amount**. Click **Add income** to record one.

![The Incomes register of Atlasworks Website Redesign with the Milestone column and the Add income button](https://storage.googleapis.com/reworkv3-public/success/260923/dM6P4mWv8jQ69PseCf72eTjUaL6nvy5HyiHIpu1r99jUZYO3QbZMd1MOAXQxy1mD/img.fFO76RZ7valERq0esMsQuneippc5TFxl3QgSa5QpNHR4rKXFV1puql0OVNZKqLca.png)

## Step 7: Book the income against a milestone

In the **Book income** dialog:

- **Name**: what's being billed, for example _Build phase invoice_.
  
- **Milestone**: the project milestone where this revenue is recognised, for example **Go-live**. Milestone billing is the default income model, and the picker also offers **No milestone** for revenue that stands alone. See [Roadmap and milestones](https://support.rework.com/article/roadmap-and-milestones).
  
- **Income type**: the kind of revenue. The list comes from the service's income types, and a type that carries a bill rate fills **Rate** in for you. A service with no income types defined shows **None** here, and you simply enter the amount.
  
- **Status**: where this money is in its lifecycle. New income starts as **Draft**.
  
- **Quantity**, **Rate** and **Amount**: the amount is quantity × rate, or type the contract figure straight into **Amount**. For a fixed fee, leave the quantity at 1.
  

Click **Book income**.

![Name, Milestone set to Go-live and Amount in the Book income dialog](https://storage.googleapis.com/reworkv3-public/success/260923/VwB51VHCwV5ln06uA3Ty5WHzFW3tMFCuSEp3e0Rnv18DUN8M1Tbtk21G2DrfY5NB/img.Y3utmwAysI89BgBIOBzU87fo3IY6LAtizSmWWTCZByOfh9QWO9p4H3NkUN8kqygS.png)

## Step 8: Move the income through its lifecycle

Income has its own lifecycle, separate from costs. Open a row's **⋯** menu:

| Status | What it means | Menu action |
| --- | --- | --- |
| **Draft** | Agreed but not billed yet. | **Mark invoiced** |
| **Invoiced** | The invoice is out, the money is not in. | **Mark received** |
| **Received** | The money has landed. | **Mark invoiced** puts it back. |
| **Cancelled** | The revenue will not arrive. | **Cancel income**, then **Revert to draft**. |

The menu only offers the moves that make sense from where the record is. On a **Draft** income it reads **Edit**, **Mark invoiced**, **Cancel income** and **Delete**.

![The row menu of a Draft income with Edit, Mark invoiced, Cancel income and Delete](https://storage.googleapis.com/reworkv3-public/success/260923/rvHp3SOyYZ1FzXZFCa1s1l6J40wWEPk7jul1rfHVCNlnKBgzBFPRNFQpmNlzFheY/img.jRqVBU7VlBS1gqYngHiXa7wrbSjtLFqAjDsdF978s3iIpiDNx8LYB73cOX8OskWE.png)

## Step 9: Confirm the amount received

Marking an income **Received** opens the **Amount received** prompt, showing what was planned. Enter what actually landed, which may be less than the invoice after tax, fees or retention, and click **Save**.

**Skip** leaves the income received but with no confirmed figure, and only confirmed figures count in the project totals. No problem if you skip it for now: you can always add it later with **Edit**.

![The Amount received prompt with the planned amount, the input, Skip and Save](https://storage.googleapis.com/reworkv3-public/success/260923/CiYLbhUBOkZYJGkLrMftMgyGVzhGxp8dM69PkoddFz5i5fyzwmFX9e0WXAqowHhY/img.nZJy2Mqc6GNyWEMsz18sPxhLQIBrmY3KEdi6E0D7pvrxs5cDJdMmmVfBlv6eBVBt.png)

Costs and income both feed the **Financials** card on the project **Overview** and the service P&L. See [Read the P&L report](https://support.rework.com/article/read-the-pnl-report).