# Roadmap and milestones

Lay out your project's phases on a timeline, set the milestones that gate them, and keep track of the deliverables each milestone needs.

Source: https://support.rework.com/article/roadmap-and-milestones

Tasks tell the team what to do this week. A roadmap tells everyone, including the client, where the project is heading: the big phases of work, and the checkpoints where someone has to say "yes, move on". In Rework Projects, the **Roadmap** section draws each phase as a bar across the calendar and each milestone as a marker below it, so the plan and the progress sit together on one screen.

> **Note:** The **Roadmap** section only appears when **Roadmap enabled** is on in the project settings. See [Set up your project](https://support.rework.com/article/set-up-your-project).

## Step 1: Open the Roadmap and click Create

- Open the project and click **Roadmap** in the project rail.
  
- Click **Create**. The menu offers two things:
  
  - **Roadmap item**: a phase, drawn as a bar with a start and an end.
    
  - **Milestone**: a dated checkpoint, drawn as a marker on the milestone lane.
    

![The Roadmap section with the Create menu open on Roadmap item and Milestone](https://storage.googleapis.com/reworkv3-public/success/260923/yTb7RoEvp9OXuxa2eWfFEIoGBpSK691rNO4G9l0uQKnVURQ1HHoW1clw5DJ0QPHx/img.bnYJoQl3HsFMifGqkHcR4QaeyElNgmMUoUk6OotLyr3VIysC5nO1ywPS9DTOeTXe.png)

## Step 2: Add the phases

Click **Roadmap item**. The **New roadmap item** form asks for:

- **Phase**: the name of the stage of work, for example _Research_.
  
- **Start date** and **End date**: where the bar begins and ends. The end date must be on or after the start date.
  
- **Owner**: who runs this phase, for example Helen. This one's optional.
  
- **Color**: the colour of the bar.
  
- **Progress**: **From tasks** fills the bar from the completed tasks linked to the phase. **Manual** lets you drag a slider instead.
  
- **Summary**: one line on what the phase delivers.
  

Click **Add roadmap item**. Repeat for each phase, for example _Identity design_ for Jolie and _Rollout_ for Harry.

![The New roadmap item form for the Research phase](https://storage.googleapis.com/reworkv3-public/success/260923/a415w80HgFZ7Vh2FGbMzBCaGzDA5PBQMmOOWYeUo1NW41gQXiZQtMp27fjSmWJDV/img.B8E5AER5XkmlW8tnFFwaBnRr09pHKnRunGDMrtk2MAetQWKlErwk6hg1NKJDcqRx.png)

## Step 3: Read the timeline

Each phase is a row with its bar across the calendar, and the owner under its name. The fill shows its progress and a red line marks today. Need to shift a phase? Drag either edge of a bar to change its dates.

Use **Week** and **Month** at the top to zoom. **Week** spreads the next few weeks across the screen, which suits short phases and close milestones. **Month** shows the whole program at once.

![Three phases on the roadmap timeline in the Week scale, with the Week and Month switch](https://storage.googleapis.com/reworkv3-public/success/260923/P68P5cA4rTXpbUVRWFVeOeT7HuLYIoBBxTqhHj3V4nvTryYDo5cGEm7BhdZgoDkv/img.6zEbLVwaLARbdr5c0chFLT0xTmMj9gOjBzT8hE14SZjPdZZvXdLnOxwK8YQKnpZW.png)

## Step 4: Add a milestone

Click **Create**, then **Milestone**. The **Create milestone** form has:

- **Name**: the checkpoint, for example _Brand sign-off_.
  
- **Target date** and **Status**: when it's due, and whether it's **Planned**, **In Progress** or **Done**.
  
- **Type**: how it gates the work:
  

| Type | Use it for |
| --- | --- |
| **Gate** | A go or no-go decision before the next phase can start |
| **Progress** | A progress check part-way through |
| **Acceptance** | The client formally accepting a deliverable |

- **Linked phases**: click the phases this milestone gates, for example _Identity design_.
  

![The top of the Create milestone form with the name, target date, status, type and linked phase](https://storage.googleapis.com/reworkv3-public/success/260923/7KOkDYIVyFigOxxLu6ptLSQF0YEdKUDnxQcZ9ktFm7udxrgxHwSSUSId6tTPyUeK/img.DXdXDk4rHlTxSzO5lLMm1WyqcJbmRnGL5GEtzrqLcSWKu8XTFcVgKE7x5W2HEMDm.png)

Further down, add a **Description** of what the checkpoint covers. Under **Key deliverables**, click **Add deliverable** once for each concrete outcome that completes the milestone, for example _Logo lockups approved_. Then click **Create milestone**.

![Key deliverables filled in and the Create milestone button](https://storage.googleapis.com/reworkv3-public/success/260923/3GiOG2lCAFP0ZPnkTYet6o1kWk9flAkTMLiR7SEdNVze44AVksN6EwNiR0WsdWYL/img.9vkJtXvMXQNkhwXijv2CEyTADYfUTN4duR1gjcPSWtFLAknfv6EgDtXGupjVFGtF.png)

## Step 5: Check a milestone on the timeline

Milestones sit on the **MILESTONES** lane under the phases. Click one to open its details card at the bottom: the status, the target date, whether it's **Overdue**, and its **Linked roadmap items**. Click **View** to open the full milestone, or **Edit** to change it.

![The Brand sign-off milestone selected on the timeline with its details card](https://storage.googleapis.com/reworkv3-public/success/260923/PIoPd8F442Z77DPtt2Ium4KrVVIgXaEfiO0DRyepvWGzdt01NFWtn0C6cWbNAtQ9/img.f5eXOM72sGPQqLgAszSc74Uj4LC7PyTvbVUMO2xpexIgcI8d2oQKTvTKF9KAWoJ0.png)

## Step 6: Track the deliverables in the milestone panel

**View** opens the milestone side panel. Here you can:

- Change the owner, the target date and the status.
  
- Tick off each item under **Key deliverables**. The heading counts how many are done. ✅
  
- Book income against the milestone, for example the invoice raised at sign-off.
  
- See its **Linked phases** and linked tasks, and discuss it in **Comments**.
  
- Use the **⋯** menu to **Edit milestone**, **View activity** or **Delete milestone**.
  

![The milestone side panel with Key deliverables and Linked phases](https://storage.googleapis.com/reworkv3-public/success/260923/yrRQ7YHikg9cxLwojaetdGKUSCcMpKkR7u1tVQlBwMYHMk0NZshtUhsyFxDFHGDe/img.Y67dmq9COiiLxzmChDscB2PbHqZPJ4eKxPcNekmx6kcatDx6jKvtVatSKShDr0PN.png)

Milestones and phases also show on each task, so you can link a task to the phase it belongs to. To plan the tasks themselves day by day, use the [Timeline view](https://support.rework.com/article/timeline-view).