# Task deliverables

Ask for proof of the work when a task is completed, either as a structured form or as a free-form note with files.

Source: https://support.rework.com/article/task-deliverables

A task marked Done tells you the work is finished. It doesn't tell you what was delivered. With deliverables, a service can ask for that proof at the moment a task is completed: a link to the final artwork, the report that went to the client, screenshots of the page that went live. The deliverable stays on the task, so anyone reviewing the project later can see what each task produced without chasing the assignee.

> **Note:** Deliverables are set up per service by an app admin. Every project under the service follows the same setting.

## Deliverable modes

| Mode | What the assignee provides |
| --- | --- |
| **None** | Nothing. Tasks complete without a deliverable. This is the default. |
| **Internal Form** | A short structured form, with fields the admin defines for the service. |
| **Free-form** | A formatted note, with screenshots pasted straight in, plus optional file attachments. |
| **Standard Output** | A record in a central output service. Marked **Coming soon** and cannot be picked yet. |

### Step 1: Open the service's Deliverables settings

- Open the service, click the **...** menu next to its name and choose **Service settings**.
  
- Click **Deliverables** in the left menu.
  
- Under **Deliverable Mode**, pick how tasks in this service should record their deliverable.
  

See [Service settings](https://support.rework.com/article/service-settings) for the other sections of this window.

![Service settings, Deliverables with the four deliverable modes and Standard Output marked Coming soon](https://storage.googleapis.com/reworkv3-public/success/260923/bgyMy1rqaUR0njtrA9zs8A2FSaGG0h6BkIKyczbsoDwokexzRdNClAm5Iv0gWonv/img.tOF0TNyJGPG6lcunHgEoFgnN4DovSCIhD8vW3zIBFb6sdtGYSfRnGn1tkiZfdCRn.png)

### Step 2: Choose Internal Form and define the fields

Pick **Internal Form** when you want the same few answers from every task, for example a link and a version number.

- Tick **Require deliverable to complete** if a task shouldn't be marked Done until its deliverable is provided.
  
- Under **Deliverable Fields**, click **Add Field** for each answer you need.
  

![Internal Form selected, with Require deliverable to complete and Add Field](https://storage.googleapis.com/reworkv3-public/success/260923/UN65pUH58MQsF4IwOkmEcf1HE5NLPR28rwUNGkV4OrjI2no51tn67mZek8dj48cZ/img.mdrglM33yFJKp16Mn4dkz5ljYaRymym9QOj3FwwD3FHAyQg37xCnafPsWJikyjJt.png)

For each field, enter a **Label**, choose a **Type** and tick **Required** if the assignee must fill it in. Use the arrows to change the order, or the bin icon to remove a field. Click **Save changes** when you're done.

![A deliverable field being defined, with Label, Type and Required](https://storage.googleapis.com/reworkv3-public/success/260923/nvP6i9gJb0jBALayGAMXALvRRKd2Jz2ppPdOLrCS2CwvgQ93TlHGqJOJzCHbz6Cy/img.i2jLJ2yEUn0f59B90MyTLPVTxzr33xjuiqyXuZp6k6SAZYY5zA1oMBO2WXJp0nsV.png)

### Step 3: Or choose Free-form

Pick **Free-form** when deliverables vary from task to task. Assignees write a note and attach files, with no fields to fill in. **Require deliverable to complete** works the same way. Click **Save changes**.

![Free-form selected, with the Free-form Deliverable explanation](https://storage.googleapis.com/reworkv3-public/success/260923/XLAItDS705PyRwB9E0EsjZo0HDtL6CqGnfTgJHdt2uKG839YDUxHOnJPKQu7R03n/img.dipxhSpA6DW8ry0JHwVvLpwiyEkcwE4jUARfI9WiSIxZPnJw15soYXHleUPVJgpG.png)

### Step 4: Provide the deliverable when you complete a task

Once a service has a deliverable mode, completing a task asks for it:

- Click the circle next to a task, or pick **Done** from its status menu. On a project with task review, the same happens when you submit the task for review.
  
- The **Task deliverable** dialog opens, showing the task's name and the mode.
  
  - For **Internal Form**, fill in the fields.
    
  - For **Free-form**, write the **Note** and use **Attach file** to add files. Screenshots can be pasted straight into the note.
    
- Click **Save & complete**. The deliverable is saved and the task moves on.
  

If the service doesn't require a deliverable, you can click **Skip** to complete the task without one. When it's required, there's no **Skip**: the dialog says _A deliverable is required to complete this task._ and **Save & complete** stays unavailable until you fill something in. Click **Cancel** to leave the task as it was.

A task that already has its deliverable completes straight away, without asking again.

### Step 5: View or change a task's deliverable

Open a task to find its **Deliverables** section.

- Before anything is provided it reads _No deliverable yet._ Click **Add deliverable** to add one without completing the task.
  
- Once provided, it shows the form's answers, or the note and attachments. Click **Edit** to change them. Attachments can be previewed or downloaded.
  

> **Note:** While a task is under review, its deliverable is locked and can't be edited. No problem: pull the task back to Active to change the deliverable, then submit it again. See [Complete a task and task review](https://support.rework.com/article/complete-a-task-and-task-review).

Your service now keeps proof of the work on every task. ✅ To add other information to tasks, see [Task details and custom fields](https://support.rework.com/article/task-details-and-custom-fields).