# Task dependencies

Link tasks that need to happen in order, see at a glance whether that order holds, and get a heads-up before work jumps the queue.

Source: https://support.rework.com/article/task-dependencies

Some work simply can't start until other work is finished. The homepage templates can't be built before the CMS is set up, and the site can't launch before QA passes. A dependency records that order on the tasks themselves, so the timeline shows it, the dates are checked against it, and anyone who tries to start or finish a task out of order gets a friendly warning first.

## How dependencies work

A dependency always joins two tasks:

- The **predecessor** is the task that has to happen first.
  
- The **successor** is the task that waits for it.
  

You add the dependency on the successor. There are three types:

| Type | Short | The successor | Example |
| --- | --- | --- | --- |
| **Finish to Start** | FS | can't start until the predecessor finishes | Build homepage templates can't start until Set up CMS finishes. |
| **Start to Start** | SS | can't start until the predecessor starts | Write the page copy can't start until Homepage wireframes starts. |
| **Finish to Finish** | FF | can't finish until the predecessor finishes | QA and accessibility pass can't finish until Contact form integration finishes. |

**Finish to Start** is the default, and it's the one you'll use most.

### Step 1: Add a dependency from the side panel

- Open the task that has to wait, the successor.
  
- In the **Dependencies** section, click **Add dependency**.
  
- Search for the task it depends on and click it.
  

The picker only offers tasks that can be linked. It leaves out the task itself, tasks that are already linked, and any task that already depends on this one, so two tasks can't end up waiting for each other.

![The Dependencies section with Add dependency and the task picker open](https://storage.googleapis.com/reworkv3-public/success/260923/re3MbTt4f3C2wa8ePHY8OUeOz1noVVWai7ObuCqEdanF4regubsVkQmQHvSXEcM3/img.HT3BvWC1SCqQHuHVHJJO8Vqqk7iMMCUERYavrfAScl90ebJcTqhPckE0JaRefeqM.png)

### Step 2: Choose the type

The dependency appears as a row with the predecessor's code and name. The **FS**, **SS** and **FF** buttons at the end of the row set its type. It starts as **FS**.

![A dependency row with the FS, SS and FF type buttons](https://storage.googleapis.com/reworkv3-public/success/260923/WOfA9Cl0NnHwZfQynOJdPLq9CA2tkS3FEiKd9W49aLqB5Q7hX2EqLPeDYlRjysU9/img.A7Wvc2fq83teW8QikOjtmkvikrxuC2L9lKnAn3EQG5HktU3CU1FRdBoiUj4ItaGk.png)

### Step 3: Check whether the dependency is satisfied

Hover the type buttons to see the dependency in full: the **Predecessor**, the **Successor**, a sentence that spells out the rule, and a check against the two tasks' dates.

- **Satisfied**: the dates respect the rule.
  
- **Not satisfied**: the dates break it, for example the successor is scheduled to start before its predecessor finishes. The row turns red.
  
- **Not scheduled**: one of the tasks has no dates yet, so there's nothing to check.
  

![The dependency detail card with the predecessor, the successor and the satisfied check](https://storage.googleapis.com/reworkv3-public/success/260923/ei6qYTwfqdRPqylymvsXZkdKMKatbWfpQQZ9XCfDa4JGPLY6hhqHgXopV1iF99ZF/img.rj5R6Te3MURGtdGrfTK9j7lw8M6ZQe2ia8tAcqIq9kLg44ldzHrpM8b2MoMxUrAQ.png)

### Step 4: Draw a dependency on the Timeline

The Timeline view shows every dependency as an arrow between two bars, labelled with its type. Arrows that aren't satisfied are drawn in red.

![The Timeline with a Finish to Start arrow from Set up CMS to Build homepage templates](https://storage.googleapis.com/reworkv3-public/success/260923/bYnLAHYCrnowM6Ky8aZt7egGb5VpSpJ36l2pAlOSsEC1kv3I0WGzKuU2ivFMbDwQ/img.rbND6ClforBNzmppbko8ObXgUQdEQ9M2rKQTKEvVj3VE5EC6TujvBZhSKB1615Nd.png)

To draw a new one:

- Open the **Timeline** view of the task board.
  
- Hover the predecessor's bar. A round handle appears at each end.
  
- Drag from a handle onto the successor's bar:
  
  - From the **finish** handle onto the **start** half of the other bar makes **Finish to Start**.
    
  - From the **finish** handle onto the **finish** half makes **Finish to Finish**.
    
  - From the **start** handle makes **Start to Start**.
    

![The start and finish link handles on a hovered Timeline bar](https://storage.googleapis.com/reworkv3-public/success/260923/2T2vo5bx5MIqfysjouJiUXGsf9OZY5w70ASTrBuGzzYnq3EUjK1msL8bbGKS3IPE/img.I4D2GkMoWB7WBJ9krSaeqrr3iyFBCFLN4wBTrsfjX687ciixOfCtnPkfFLzM5G0N.png)

Click an arrow to open its card. From there you can switch the **Type** or **Remove** the dependency.

![The dependency card opened from an arrow on the Timeline, with the type buttons and Remove](https://storage.googleapis.com/reworkv3-public/success/260923/YUfokqwNgqS2cTfjQYiZ8s4iVK1Pv1qG7T6oNtLG0ez7kALbU6ji4c88UZRPaTcY/img.hMod5eZD30kI0WbGROEAOM90UdtgqYDVaiOorDxK1Vg0inaitTGjf3BtwgPdFBep.png)

### Step 5: Start or finish a task whose dependencies aren't ready

Rework Projects doesn't block work that runs out of order, because sometimes that's the right call. It just asks you first.

When you start or complete a task and one of its dependencies isn't ready, a dialog lists each one: the predecessor, what it still owes (for example _Must finish before this task starts_), who's assigned to it and its status.

- Click **Go back** to leave the task as it is and follow up with the predecessor's assignee.
  
- Click the button that names the move, such as **Start anyway**, **Mark as done anyway** or **Submit for review anyway**, to go ahead.
  

![The dependency warning when starting a task whose predecessor has not finished](https://storage.googleapis.com/reworkv3-public/success/260923/kZuarJ3VIX634EarO7gOSHE4yff04MqavMTlLohRpSQNha0WsfdNJQo1phYjhbGK/img.HuIDTAwWWptqJyWh0ySYS6Zk3LEaaBMar4GeYggHxoebLW0HQZclYFgiY5hPATBT.png)

Which moment is checked depends on the type:

| Type | Checked when you start the successor | Checked when you finish the successor |
| --- | --- | --- |
| **FS** | The predecessor must be Done | The predecessor must be Done |
| **SS** | The predecessor must be Active or Done | The predecessor must be Active or Done |
| **FF** | Not checked | The predecessor must be Done |

### Step 6: Remove a dependency

- Open the successor and find the dependency in **Dependencies**.
  
- Hover the row and click the bin icon at its end.
  

You can also click the arrow on the Timeline and choose **Remove**. Don't worry: removing a dependency leaves both tasks exactly as they are.

![A dependency row with the remove button showing](https://storage.googleapis.com/reworkv3-public/success/260923/ASHqZfBBHpKir6xXpBIxntp4WD0ld7VYwMtI72ttSRng46CVkzUhOvaUE2CvTnwG/img.qrnWmZRaJDAye1wrJa8w1MOWm12y6MrCt9IUt8aV7zwYMHxbtY3bB1u14Sj5V1mg.png)

With the order of work on record, the Timeline shows you where the plan is at risk. When a task is ready, finish it with [Complete a task and task review](https://support.rework.com/article/complete-a-task-and-task-review) ✅
