# Timeline view

Plan tasks as bars on a calendar, link them with dependencies, and see each parent task's sub-tasks wrapped in one bracket.

Source: https://support.rework.com/article/timeline-view

A list tells you what's due. A timeline shows you what happens when something slips. The **Timeline** view draws every task on a board as a bar from its start date to its deadline, links tasks that depend on each other, and wraps a parent's sub-tasks in a bracket. You get to see the whole plan, and move it just by dragging.

## Step 1: Open the Timeline and set the time period

Open a board and click the **Timeline** tab. Then use the toolbar:

- The time period dropdown: **Week**, **Month**, **Quarter** or **Year** fix how much of the calendar one screen holds. **Flexible** lets the zoom buttons move smoothly from one period to the next.
  
- **Today**: scroll the chart back to today.
  
- **−** and **+**: zoom out and in. In a fixed period they narrow or widen the columns. In **Flexible** they cross into the next period when you pass the limit.
  

![The time period menu open, with Today and the zoom buttons](https://storage.googleapis.com/reworkv3-public/success/260923/5jPGl5na004EqQWvBk7LHKV1tBtK1B5tq9AAu6YIL4GeHKNJDwicWon1lEe9Qmfg/img.lVQvYJH5ALf6aUzDS64aHDUG2bduvyd1hdmmDz57D9jHDmqCZmAw20SEx6Ryp4PU.png)

## Step 2: Read the chart

- The button at the left of the toolbar hides or shows the task table, the column of task names and groups. Hide it to give the chart the whole width.
  
- The vertical line marks today.
  
- Each bar runs from the task's start date to its deadline. The avatar next to it is the assignee. Hover a bar for a preview card with the dates, duration, owner, assignee and priority, and click it to open the task.
  
- Drag a bar to move both dates, or drag either end to change just the start or the deadline.
  

![The timeline in Month with the task table toggle, the today line and a task bar](https://storage.googleapis.com/reworkv3-public/success/260923/1fTmoAocPPuUVUmMtuWNIuAhKRDrpHNVm9nII9vA78WuvRC5V8g3OxU7kgasOn1i/img.DldFl5kb5RsYLIrBt6qsr6mM8txswlBLONECrjunHLIfnBjzm8Abo5lIz8E78sXK.png)

## Step 3: Link tasks with dependencies

A dependency says one task has to wait for another. Hover a bar and small handles appear at both ends. Drag from one bar's handle to another bar:

| Drag from | To | Type | Means |
| --- | --- | --- | --- |
| The finish of A | The start of B | **FS** Finish-to-Start | B can't start until A finishes |
| The start of A | The start of B | **SS** Start-to-Start | B can't start until A starts |
| The finish of A | The finish of B | **FF** Finish-to-Finish | B can't finish until A finishes |

The connector carries a tag with its type. A red tag means the dates break the rule, for example _Color palette_ starts before _Moodboards_ finishes.

![Dependency connectors on the timeline with their FS and SS tags](https://storage.googleapis.com/reworkv3-public/success/260923/lv5as9TV0hcbp0w1woUG8dcASIFj99Xmahk1P3aQJf50OfVKalvo6qgRoSadJlRo/img.n4Hbo4Sojc3iWcdCUKqEvDYz3PivbfL1AtiJuzwLEop1Mo1vogrjBdfG5xgtpi83.png)

## Step 4: Check or change a dependency

Click a connector's tag to open it:

- **PREDECESSOR** and **SUCCESSOR** name the two tasks, with a sentence that spells out the rule.
  
- **Satisfied** or **Not satisfied** says whether the current dates respect it, and why.
  
- **Type**: switch between **FS**, **SS** and **FF**.
  
- **Remove**: delete the dependency. Don't worry, the tasks themselves stay.
  

![The dependency popover with the predecessor and successor, the type switch and Remove](https://storage.googleapis.com/reworkv3-public/success/260923/0joTNfzqX85lsj053dOjx74xPgheHyLbdceiamW8jen3p5ClW45x56d7FVRJKLI4/img.rtMfqWUlDgoDEopzNSiefPBIk2hEiMWU61OzbeRFwK1punLDSkIc6xjCAwTuchIu.png)

## Step 5: See sub-tasks under their parent

When a task has sub-tasks, the task table nests them under it. On the chart, a dashed **summary bracket** wraps the parent and its sub-tasks, so you can see the span of the whole piece of work at a glance. For example, _Brand guide draft_ wraps _Guide layout_ and _Guide copy_.

![Brand guide draft with its sub-tasks in the task table and the summary bracket on the chart](https://storage.googleapis.com/reworkv3-public/success/260923/IbZBS150g0OGpQs3yYaeKorfkprvxJESSYwPpEU7qEd7sFaZZK0DxGaByvvW9iym/img.AUdADjP55MySrXWfJZpPIQNNtpjBBvkxgtSaoOK7CrvXFK5RJze83TcBXQaxVqnG.png)

## Step 6: Choose what the timeline shows

Click **Customize view**. Under **DISPLAY**:

- **Show undated tasks**: list tasks with no start date or deadline. They appear without a bar.
  
- **Show task table**: the same as the toggle button in the toolbar.
  
- **Show summary bracket**: the dashed bracket around a parent's sub-tasks.
  

Under **FIELDS**, pick the columns the task table shows next to the name. Like any view change, these only stick once you click **Save view**. See [Filter, group and save a view](https://support.rework.com/article/filter-group-and-save-a-view).

![The Customize view panel for a timeline with the three display switches](https://storage.googleapis.com/reworkv3-public/success/260923/YNHU64kwUpUyVF9FZLuAkhVarFu9hBjxCMfcEg6I0Szmxx8zM8BSzBcjqfW7vRUg/img.HwUxCkrDp8dDv453c7tWZLJoUm8FTRAmnZgIGBnrhvws7v0CZo4cS9mabxvx0PF8.png)

## Step 7: Schedule an undated task

With **Show undated tasks** on, a task with no dates sits in its group with an empty row. Hover the row on the chart and a **Drag to schedule** marker follows the cursor. Drag across the days the task should take, and the start date and deadline are set from where you start and stop. 💡

![An undated task in the task table and the Drag to schedule marker on its row](https://storage.googleapis.com/reworkv3-public/success/260923/PIrvDYPC99NLawKIsec4ncSsN7CiiZ6Kq37J6Je0URBVIF3hYOQyj5dAAPLz3YRV/img.VYIKisRvTvqwoWJqKXH31KKYDglgHscWhGp81asVJcfhiVG5r3ckCiYs8JZCows9.png)

> **Note:** The timeline plans tasks on one board. To lay out the project's big phases and milestones, use the [Roadmap](https://support.rework.com/article/roadmap-and-milestones).