# Track time and log it to workloads

Run the timer while you work, log hours by hand when you forget, and turn tracked time into the actual effort on a booking.

Source: https://support.rework.com/article/track-time-and-log-it-to-workloads

Tracked time only pays for itself if it reaches the numbers the studio is judged on. Rework keeps the two jobs separate on purpose: the timer records **what you did with your day**, and a workload booking records **what the project is charged for**. Logging time to a workload is the deliberate step between them, so a long Tuesday doesn't silently become a cost overrun. Here's how to run the timer, log time by hand and move it onto a booking.

## Step 1: Start a work session from the header

The timer lives in the app header, next to the notification bell, and follows you across every page.

- Click the timer icon to open the panel.
  
- Type what you're doing in **What are you working on?**
  
- Optionally, use **Link a task (optional)** to bind the session to a task before it starts, so the time lands on the right work without a second step.
  
- Click **Start**.
  

![The header timer icon and the open panel with What are you working on and the Start button](https://storage.googleapis.com/reworkv3-public/success/260923/hQJElg2keQRyvZaiXjOayf0gLEmZ1RUwD0kQO7dZAuKSlgR7fQgcW9J7DNocADNR/img.pjajbyRN8h6emnVCWQQ5gIMn9oHiAaYYgSUtTtdPMNV5HvxxO9fBvlojHESLpqNR.png)

> **Note:** You can also start from a task. On a task, **Start** opens a session already bound to it, and **Add to sessions** parks it in your queue without starting the clock.

## Step 2: Watch the clock in the header

Once a session is running, the icon becomes a pill showing the elapsed time, visible on every screen. The controls beside it act on the session on the clock:

- **Pause** keeps the time already on the session and stops counting.
  
- **Stop & log** ends the session and writes it to your time logs.
  

![The running timer pill in the header with its pause and stop controls](https://storage.googleapis.com/reworkv3-public/success/260923/a1WgjqkWJxnlGFUnvrxPumG98L6vkzAvjjdZJDRK5cnGXzCM9rp9JcJ5hRJWgiDl/img.76w0Iv0BBAH7NI9RWILJKAGCN1XHayLwayt5JgYICFNhKZk5SFaFjP3iT8Ge2rGD.png)

## Step 3: Pause, resume and stop from the panel

Click the clock on the pill to open the panel. The card at the top, headed **NOW TRACKING**, speaks for the session on the clock:

- **Pause** holds it, and the same button then reads **Resume**.
  
- **Stop** asks **Stop and log this session?** before it commits, because the session is gone afterwards.
  
- **SESSIONS** below lists everything parked behind the running one, and one click switches the clock onto any of them.
  
- **What's next?** with **Add** starts or parks another session without leaving the panel.
  

![The timer panel with the NOW TRACKING card, the Pause and Stop buttons and the sessions queue](https://storage.googleapis.com/reworkv3-public/success/260923/8duv8raVwqw2MJR2y3uAIpIyp0mw4nLjeatj4f1plpBLtaHwoobj4DMclBCPOKrv/img.CzRwW7DRI3fomW2VId3QAJ3BOO0RLHu6Dx7D0nrpl0Sq3EwrB4VNATvFsNC4jqHh.png)

## Step 4: Review your sessions in My Works

Open **My Works** and click **Work Sessions** to see your own tracking: sessions grouped by day, with a **Week Summary** giving **Total time**, **Working time**, **Break time**, the daily average, the number of **Sessions** and how many days were active.

This page is just for you. To see effort across the team, use the [workload and capacity views](https://support.rework.com/article/capacity-and-workload-views).

![The Work sessions page in My Works with the week summary](https://storage.googleapis.com/reworkv3-public/success/260923/DZBR3etPq5axNa8Bi2PELvTeKrTxuD6e7zz1eKSQKyZiNvcoBk4zSGevyETGX11g/img.fq1OUlkHQqvwwUgUq8yg6d4QZKoRMcX5fYYBZBUQaOHZb16qxhAAJdNvRk7L87Kq.png)

## Step 5: Open Tracking on a task

Everything a task costs is gathered in one collapsible **Tracking** section on the task, with a summary line of planned against actual. Open a task and expand **Tracking**. It has three tabs:

| Tab | What it holds |
| --- | --- |
| **Workloads** | The effort bookings made against this task, with **Log workload** to add one. |
| **Time** | The work sessions logged on this task, with **Add time** and **Log to workload**. |
| **Costs** | Direct expenses logged against this task. |

Once a task has something on it, each tab carries a count and the section header shows a one-line summary, for example _2d planned · 0%_.

![The Tracking section on a task with the Workloads, Time and Costs tabs](https://storage.googleapis.com/reworkv3-public/success/260923/WOLcuH9vJKbLIX4q2V2GNIX8nkpffjDNTngLzpdtNOdJYoCtG6HHAYrt0oU4PsvY/img.Sz6pKBTsfPi0RZz5xI6YuJMJ5v8PAiq0SB0rQlGyOMqSlEMwfvFBOSbxJEcKTrXg.png)

## Step 6: Add time by hand

Forgot to start the clock? No problem. Open the **Time** tab and click **Add time**:

- Enter the hours in **Hrs**.
  
- Say what you did in **What did you work on?**
  
- Set the date and time the work started.
  
- Click **Log time**.
  

The entry joins the list under its day, and **Total logged** at the top adds it up.

![The Add time composer on the Time tab with the hours, the note and the Log time button](https://storage.googleapis.com/reworkv3-public/success/260923/sk35Dndai7yElD4ZfJhOTIiaFMslXJJnc2jZPxliMOP2DtSx9EJwc02COm0oaA2m/img.uAzjjxjVx7NL5rdFl55m0soN0LGl3bCIA0JO43uZQYMSdfgUBRZiGHnHHKtlwIOB.png)

## Step 7: Log the time to a workload

Tracked hours don't touch project cost on their own. **Log to workload** is the step that turns them into actual effort on a booking.

- Click **Log to workload** on the **Time** tab.
  
- The top of the dialog shows how much is **logged on this task**, and how many sessions and people it came from.
  
- Each of the task's workload bookings gets a row. Type how much of that time should count against it, in the booking's own unit, for example 0.75 of a day.
  
- The bar compares what you've **Allocated** with what was logged, and warns you when you go over.
  
- Click **Record**.
  

Each booking's actual effort is set to the quantity you typed, and its actual cost to that quantity at the booking's cost rate. This is a guide, not a rule: allocate only the time that should count toward cost, and time spent but not billable simply stays in the time logs.

![The Log time to workloads dialog with the logged total, a booking allocation row and the Record button](https://storage.googleapis.com/reworkv3-public/success/260923/vyNmNs4UesCeCfh7i6iMbCHdmbrJdcclX4yWocrqy3bFnrp5yYJGRQAit6xZEE8g/img.FCitLMP8eSKjgaBryQ0oOhVRHXO2eArlJLvhrwD8N1N8yEwsGNx7m8tkmVa6t31R.png)

> **Note:** A task with no workload bookings has nothing to record into. Book one first from the **Workloads** tab with **Log workload**, or see [Book workloads](https://support.rework.com/article/book-workloads).

Once recorded, the booking shows its actual in the **Recorded** column on the project's [Workloads and Costs](https://support.rework.com/article/record-costs-and-income) pages, and the difference between booked and recorded is what the [P&L report](https://support.rework.com/article/read-the-pnl-report) reads as margin.