Timeline view
Plan tasks as bars on a calendar, link them with dependencies, and see each parent task's sub-tasks wrapped in one bracket.
A list tells you what's due. A timeline shows you what happens when something slips. The Timeline view draws every task on a board as a bar from its start date to its deadline, links tasks that depend on each other, and wraps a parent's sub-tasks in a bracket. You get to see the whole plan, and move it just by dragging.
Step 1: Open the Timeline and set the time period
Open a board and click the Timeline tab. Then use the toolbar:
The time period dropdown: Week, Month, Quarter or Year fix how much of the calendar one screen holds. Flexible lets the zoom buttons move smoothly from one period to the next.
Today: scroll the chart back to today.
− and +: zoom out and in. In a fixed period they narrow or widen the columns. In Flexible they cross into the next period when you pass the limit.

Step 2: Read the chart
The button at the left of the toolbar hides or shows the task table, the column of task names and groups. Hide it to give the chart the whole width.
The vertical line marks today.
Each bar runs from the task's start date to its deadline. The avatar next to it is the assignee. Hover a bar for a preview card with the dates, duration, owner, assignee and priority, and click it to open the task.
Drag a bar to move both dates, or drag either end to change just the start or the deadline.

Step 3: Link tasks with dependencies
A dependency says one task has to wait for another. Hover a bar and small handles appear at both ends. Drag from one bar's handle to another bar:
| Drag from | To | Type | Means |
|---|---|---|---|
| The finish of A | The start of B | FS Finish-to-Start | B can't start until A finishes |
| The start of A | The start of B | SS Start-to-Start | B can't start until A starts |
| The finish of A | The finish of B | FF Finish-to-Finish | B can't finish until A finishes |
The connector carries a tag with its type. A red tag means the dates break the rule, for example Color palette starts before Moodboards finishes.

Step 4: Check or change a dependency
Click a connector's tag to open it:
PREDECESSOR and SUCCESSOR name the two tasks, with a sentence that spells out the rule.
Satisfied or Not satisfied says whether the current dates respect it, and why.
Type: switch between FS, SS and FF.
Remove: delete the dependency. Don't worry, the tasks themselves stay.

Step 5: See sub-tasks under their parent
When a task has sub-tasks, the task table nests them under it. On the chart, a dashed summary bracket wraps the parent and its sub-tasks, so you can see the span of the whole piece of work at a glance. For example, Brand guide draft wraps Guide layout and Guide copy.

Step 6: Choose what the timeline shows
Click Customize view. Under DISPLAY:
Show undated tasks: list tasks with no start date or deadline. They appear without a bar.
Show task table: the same as the toggle button in the toolbar.
Show summary bracket: the dashed bracket around a parent's sub-tasks.
Under FIELDS, pick the columns the task table shows next to the name. Like any view change, these only stick once you click Save view. See Filter, group and save a view.

Step 7: Schedule an undated task
With Show undated tasks on, a task with no dates sits in its group with an empty row. Hover the row on the chart and a Drag to schedule marker follows the cursor. Drag across the days the task should take, and the start date and deadline are set from where you start and stop. 💡

Note: The timeline plans tasks on one board. To lay out the project's big phases and milestones, use the Roadmap.