Complete a task and task review

Move a task through its statuses, and add a review step so a second person signs off before a task counts as done.

A project's progress is only as honest as its statuses. When a task says Done, your team should be able to trust that the work is finished, not just that someone clicked a box. Rework Projects keeps statuses simple: one click moves a task forward. And for work that needs a second pair of eyes, a project can add a review step, so a task only becomes Done once a reviewer approves it.

Task statuses

Every task has one of five statuses.

StatusMeaning
DraftPlanned but not started. New tasks begin here.
ActiveWork is under way.
DoneFinished.
FailedTried and did not succeed.
DiscardedNo longer needed. It stays on record but no longer counts as open work.

On a project with task review turned on, an Active task can also be In Review. In Review isn't a sixth status: the task stays Active while it waits for a reviewer, and shows In Review everywhere it appears.

Step 1: Complete a task with one click

  • On a task board, each task has a circle to the left of its name. The Status column shows where the task stands.

  • Click the circle to move the task one step forward. What the click does depends on the task's status, and the tooltip names it:

The task isOne clickTooltip
Draft, Failed or DiscardedStarts it, moving it to ActiveStart
Active, on a project without reviewCompletes itMark done
Active, on a project with reviewSubmits it for reviewSubmit for review
In Review, and you are a reviewerApproves it, moving it to DoneApprove
In Review, and you are not a reviewerPulls it back to ActiveReturn to work
DoneReopens itReopen
A task row's completion circle and its Status cell on the board

Step 2: Pick a status directly

To jump to any status, for example to mark a task Failed or Discarded, open the task and click its status next to the circle. The menu lists every status, with In Review between Active and Done when the project runs review.

The status menu on a task's side panel

Note: Only the assignee, the project's managers and its reviewers can change a task's status. Everyone else sees the status but can't change it.

Task review

Step 3: Submit a task for review

On a project with review turned on, finishing a task hands it to a reviewer instead of closing it.

  • Open the task and click the circle next to its status. The tooltip reads Submit for review.

For example, Jolie finishes the product page mockups and submits them. Quinn, the project's reviewer, now has to sign off.

The completion circle on a task's side panel, ready to submit for review

The task now reads In Review, and each reviewer gets a reminder to review it. On a project with review, only a reviewer or a project manager can mark a task Done. Everyone else finds Done greyed out in the status menu, with the note Only a reviewer can approve this task once the task is under review. That's expected, not an error.

The task under review, with Done locked in the status menu

Step 4: Approve or return the task

Reviewers find the task marked In Review on the board. For a reviewer, the circle on the row approves the task.

A task under review on the board, as the reviewer sees it

A reviewer has two choices:

  • Approve: click the circle, or pick Done from the status menu. The task is complete.

  • Return to work: pick Active from the status menu. The task goes back to the assignee to change, and leaves review.

Changed your mind after submitting? No problem. If the assignee wants to make a change before the reviewer gets to it, they can pull the task back the same way, with the circle or by picking Active.

The reviewer's status menu with Active to return the task and Done to approve it

Once approved, the task shows Done with a filled circle. ✅

The approved task showing Done on the board

Note: If the task's service requires a deliverable, the assignee is asked for it when they submit the task for review. See Task deliverables. If the task depends on work that isn't finished yet, you're warned before it moves. See Task dependencies.

Step 5: Turn on task review for a project

Note: You need to be a manager of the project to change its settings.

  • Open the project and click Settings in the left panel.

  • In Task review, turn on Enabling task review feature.

  • Assigned reviewers: add the people who approve tasks. The project's managers can always review, even when they're not on the list.

  • Enable review SLAs: turn on to give reviewers a deadline, then enter the SLA in hours. Each reviewer gets a reminder that is due when the time runs out.

  • Review of subtasks: turn on Also enable reviewing subtasks to send sub-tasks through the same review. Two more options appear:

    • Automatically assign the task creator as a reviewer: the person who created a sub-task can approve it too.

    • Also enable SLA for reviewing subtasks: gives sub-tasks their own review clock, set in SLAs for reviewing subtasks.

  • Click Save.

Turning review off later keeps these settings, so turning it back on restores them.

Project Settings, Task review with reviewers, the review SLA and sub-task review options

Your project now has a clear finish line for every task. To make sure the work behind a Done task is on record, see Task deliverables.