Task dependencies

Link tasks that need to happen in order, see at a glance whether that order holds, and get a heads-up before work jumps the queue.

Some work simply can't start until other work is finished. The homepage templates can't be built before the CMS is set up, and the site can't launch before QA passes. A dependency records that order on the tasks themselves, so the timeline shows it, the dates are checked against it, and anyone who tries to start or finish a task out of order gets a friendly warning first.

How dependencies work

A dependency always joins two tasks:

  • The predecessor is the task that has to happen first.

  • The successor is the task that waits for it.

You add the dependency on the successor. There are three types:

TypeShortThe successorExample
Finish to StartFScan't start until the predecessor finishesBuild homepage templates can't start until Set up CMS finishes.
Start to StartSScan't start until the predecessor startsWrite the page copy can't start until Homepage wireframes starts.
Finish to FinishFFcan't finish until the predecessor finishesQA and accessibility pass can't finish until Contact form integration finishes.

Finish to Start is the default, and it's the one you'll use most.

Step 1: Add a dependency from the side panel

  • Open the task that has to wait, the successor.

  • In the Dependencies section, click Add dependency.

  • Search for the task it depends on and click it.

The picker only offers tasks that can be linked. It leaves out the task itself, tasks that are already linked, and any task that already depends on this one, so two tasks can't end up waiting for each other.

The Dependencies section with Add dependency and the task picker open

Step 2: Choose the type

The dependency appears as a row with the predecessor's code and name. The FS, SS and FF buttons at the end of the row set its type. It starts as FS.

A dependency row with the FS, SS and FF type buttons

Step 3: Check whether the dependency is satisfied

Hover the type buttons to see the dependency in full: the Predecessor, the Successor, a sentence that spells out the rule, and a check against the two tasks' dates.

  • Satisfied: the dates respect the rule.

  • Not satisfied: the dates break it, for example the successor is scheduled to start before its predecessor finishes. The row turns red.

  • Not scheduled: one of the tasks has no dates yet, so there's nothing to check.

The dependency detail card with the predecessor, the successor and the satisfied check

Step 4: Draw a dependency on the Timeline

The Timeline view shows every dependency as an arrow between two bars, labelled with its type. Arrows that aren't satisfied are drawn in red.

The Timeline with a Finish to Start arrow from Set up CMS to Build homepage templates

To draw a new one:

  • Open the Timeline view of the task board.

  • Hover the predecessor's bar. A round handle appears at each end.

  • Drag from a handle onto the successor's bar:

    • From the finish handle onto the start half of the other bar makes Finish to Start.

    • From the finish handle onto the finish half makes Finish to Finish.

    • From the start handle makes Start to Start.

The start and finish link handles on a hovered Timeline bar

Click an arrow to open its card. From there you can switch the Type or Remove the dependency.

The dependency card opened from an arrow on the Timeline, with the type buttons and Remove

Step 5: Start or finish a task whose dependencies aren't ready

Rework Projects doesn't block work that runs out of order, because sometimes that's the right call. It just asks you first.

When you start or complete a task and one of its dependencies isn't ready, a dialog lists each one: the predecessor, what it still owes (for example Must finish before this task starts), who's assigned to it and its status.

  • Click Go back to leave the task as it is and follow up with the predecessor's assignee.

  • Click the button that names the move, such as Start anyway, Mark as done anyway or Submit for review anyway, to go ahead.

The dependency warning when starting a task whose predecessor has not finished

Which moment is checked depends on the type:

TypeChecked when you start the successorChecked when you finish the successor
FSThe predecessor must be DoneThe predecessor must be Done
SSThe predecessor must be Active or DoneThe predecessor must be Active or Done
FFNot checkedThe predecessor must be Done

Step 6: Remove a dependency

  • Open the successor and find the dependency in Dependencies.

  • Hover the row and click the bin icon at its end.

You can also click the arrow on the Timeline and choose Remove. Don't worry: removing a dependency leaves both tasks exactly as they are.

A dependency row with the remove button showing

With the order of work on record, the Timeline shows you where the plan is at risk. When a task is ready, finish it with Complete a task and task review ✅