Record costs and income
Log the money a project spends and the money it brings in, so the project's margin is always current.
Effort is only half of what a project costs. The other half is everything you buy for it: licences, stock photography, a testing lab, a freelancer's invoice. Costs collects that spend beside the labour already booked as workloads, and Incomes records the money coming back in, anchored to the milestone that earns it. Keep both current and the project's margin is a fact rather than a guess. Here's how to record them.
Note: Every amount is shown in the project's currency. Set it once in the project Settings, see Set the project billing and units.
Step 1: Open the Costs register
Open the project and click Costs in the project menu.
The Filters rail lists the categories actually in use, with a count each, and filters by Board, Status and Owner.
Click Add expense to record a new one.

Step 2: Describe the expense and its amount
In the Add expense dialog:
Name: what the money is for, for example Usability testing lab.
Quantity and Rate: how many units and the price per unit.
Amount: quantity ร rate. It updates as you type, and you can type the figure in directly when there's no sensible unit price.
Currency: the ISO currency of the expense. When the project locks bookings to its own currency, this field is fixed.

Step 3: Choose a category and a status
Category sorts the spend in the rail and in reporting. Pick one of Capex, Opex, Vendor, Labor, Infra or Other. An expense with no category is grouped as Uncategorized.
Status works exactly like a workload's: Planned for spend you expect, Booked for spend that's committed, and Recorded for money actually paid. A new expense starts as Booked.

| Category | Typical use in a studio |
|---|---|
| Capex | Equipment bought for the project. |
| Opex | Running costs such as subscriptions. |
| Vendor | A supplier or freelancer invoice. |
| Labor | People costs entered as money rather than as a workload booking. |
| Infra | Hosting, environments, tooling. |
| Other | Anything that fits nowhere else. |
Step 4: Set the owner and the period, then save
Owner: who holds this cost, usually whoever approves or receives the invoice.
Period start and Period end: the window the spend belongs to. Reports read this for phasing.
Description: invoice references, supplier details, anything that explains the number later.
Click Add expense.

Step 5: Read the register
The Costs register shows more than expenses. Every workload booked on the project appears here too, because labour is a cost:
A row tagged EXPENSE is money you entered here.
A row tagged WORKLOAD is a booking from Book workloads, shown in the Labor category with its effort, for example Labor ยท 12 day.
Booked is the committed amount. Recorded is what has actually been paid or consumed, and stays blank until the record is marked Recorded.
That's why the Costs page is the single answer to "what is this project costing us?", while the Workloads page answers "who is doing the work?".

Step 6: Open the Incomes register
Click Incomes in the project menu. Each line shows its Code, the income, the Milestone it's recognised at, its Status, the Owner and the Amount. Click Add income to record one.

Step 7: Book the income against a milestone
In the Book income dialog:
Name: what's being billed, for example Build phase invoice.
Milestone: the project milestone where this revenue is recognised, for example Go-live. Milestone billing is the default income model, and the picker also offers No milestone for revenue that stands alone. See Roadmap and milestones.
Income type: the kind of revenue. The list comes from the service's income types, and a type that carries a bill rate fills Rate in for you. A service with no income types defined shows None here, and you simply enter the amount.
Status: where this money is in its lifecycle. New income starts as Draft.
Quantity, Rate and Amount: the amount is quantity ร rate, or type the contract figure straight into Amount. For a fixed fee, leave the quantity at 1.
Click Book income.

Step 8: Move the income through its lifecycle
Income has its own lifecycle, separate from costs. Open a row's โฏ menu:
| Status | What it means | Menu action |
|---|---|---|
| Draft | Agreed but not billed yet. | Mark invoiced |
| Invoiced | The invoice is out, the money is not in. | Mark received |
| Received | The money has landed. | Mark invoiced puts it back. |
| Cancelled | The revenue will not arrive. | Cancel income, then Revert to draft. |
The menu only offers the moves that make sense from where the record is. On a Draft income it reads Edit, Mark invoiced, Cancel income and Delete.

Step 9: Confirm the amount received
Marking an income Received opens the Amount received prompt, showing what was planned. Enter what actually landed, which may be less than the invoice after tax, fees or retention, and click Save.
Skip leaves the income received but with no confirmed figure, and only confirmed figures count in the project totals. No problem if you skip it for now: you can always add it later with Edit.

Costs and income both feed the Financials card on the project Overview and the service P&L. See Read the P&L report.